A life so good, your guests will never want to leave.
When you host your friends and family, your guests will feel
right at home. Sometimes, maybe too much.
Cluster IJK: 24/24 Units Got Certified + Common area Certification in progress, I cluster clear and JK attending final QA snag points - Mar 2025
Cluster IJK: J&K cluster terrace Area final finishing along with QA snag. And I cluster Entrance Area final finishing along with External Development - Mar 2025
Cluster LMN: units QA Certification completed 24/24 + common area QA certification in Progress + Terrace area Finishing completed - Mar 2025
Cluster OPQ: QA certification started in OPQ cluster and External Painting + Internal Painting + Door & Window works in Progress QAC-23/24 - Mar 2025
Cluster RST: External Paint+ Internal Paint and Door & Window works in Progress. Units QA Certification started. QAC 17/24 - Mar 2025
Cluster UV: External paint completed. internal Painting, tiling, door and window works in Progress. QA Certification started. And Cluster WX – External paint completed. internal Painting, tiling, door and window works in Progress. QA Certification started - Mar 2025
External Development: 85% of External Development works are completed and remaining in Progress - Mar 2025
Cluster IJK: 24/24 Units Got Certified + Common area Certification in progress, I cluster clear and JK attending final QA snag points - Feb 2025
Cluster IJK: J&K cluster terrace Area final finishing along with QA snag. I cluster Entrance Area final finishing along with External Development - Feb 2025
Cluster LMN: units QA Certification completed 24/24 + common area QA certification in Progress + Terrace area Finishing completed - Feb 2025
Cluster OPQ: QA certification started in OPQ cluster and External Painting + Internal Painting + Door & Window works in Progress QAC-18/24 - Feb 2025
Cluster RST: External Paint+ Internal Paint and Door & Window works in Progress. Units QA Certification started. QAC 9/24 - Feb 2025
Cluster UV :External paint completed. internal Painting, tiling, door and window works in Progress. Cluster WX - External paint completed. internal Painting, tiling, door and window works in Progress - Feb 2025
External Development: 80% of External Development works are completed and remaining in Progress - Feb 2025
Cluster IJK: 24/24 Units Got Certified + Common area Certification in progress, I cluster clear and JK attending final QA snag points - Jan 2025
Cluster IJK: J&K cluster terrace Area final finishing along with QA snag. Cluster IJK - I cluster Entrance Area final finishing along with External Development - Jan 2025
Cluster LMN: units QA Certification completed 24/24 + common area QA certification in Progress + Terrace area Finishing completed - Jan 2025
Cluster OPQ: QA certification started in O cluster and External Painting + Internal Painting + Door & Window works in Progress QAC-13/24 - Jan 2025
Cluster RST: External Paint+ Internal Paint and Door & Window works in Progress. Units QA Certification started. QAC 5/24 - Jan 2025
Cluster UV: Plastering completed. Painting, tiling, door and window works in Progress. Cluster WX – Plastering completed. Painting, tiling, door and window works in Progress - Jan 2025
External Development: 75% of External Development works are completed and remaining in Progress - Jan 2025